Payment Protection for Construction Subcontractors: 5 Checks Before You Mobilize
Before you order materials or put a crew on site, answer two questions: How much cash will you spend before the first payment arrives, and what will you do if that payment doesn’t come?
Before you order materials or put a crew on site, answer two questions: How much cash will you spend before the first payment arrives, and what will you do if that payment doesn’t come? Your subcontract and billing schedule answer the first question. Delos Payment Protection can help with the second: you can arrange a buyer in advance for qualifying invoices if the payer doesn’t pay.
1. Confirm who owes you and what starts the payment clock
The owner may be funding the project, but your agreement may be with the general contractor. Check the legal name of the company responsible for your payment. Then ask what starts the payment clock: submission of the pay application, approval, or another event specified in the subcontract. If the wording ties your payment to money coming from someone upstream, ask how that works before you price the job.
2. Get the first pay application deadline in writing
Ask for the cutoff date, the name of the person who approves your work, and the documents they expect. If you need to bill for materials before installation, ask whether the subcontract allows it and what proof you’ll need. A missed cutoff can mean another round of payroll before you see the first payment.
The AIA’s subcontractor contract guide shows how a pay application can separate completed work, stored materials, approved changes, and retainage. Use the forms and deadlines required for your project.
3. Budget for the cash you’ll spend, not the amount you’ll bill
Say you expect to spend $25,000 on labor and materials before your first draw. If $30,000 of work is approved and your subcontract holds back 10% in retainage, you’d expect $27,000 from that draw before any other deductions. The other $3,000 follows the retainage release terms.
That $27,000 doesn’t pay this week’s crew until it reaches your account. If a delay means spending another $9,000 before it arrives, you’ll need to carry $34,000, not $25,000. Run that scenario before you commit to the start date.
4. Agree who can authorize extra work
When the site team asks you to move a connection or add a run, find out who can approve the change, how it gets priced, and when it goes into the next pay application. Keep unapproved extras separate from the amount you expect to collect on the first draw. Don’t budget payroll against a change order that hasn’t been signed off.
5. Arrange a buyer for qualifying invoices before you bill
With Delos Payment Protection, you can send a draft or signed subcontract for review before you invoice. If you agree to the terms and pay the commitment fee, Delos commits to buying invoices that meet those terms, within an agreed amount and period. If the payer doesn’t pay, you can offer a qualifying invoice to Delos. When Delos buys it, it advances up to 90% of the invoice value and handles collection under the agreement.
Payment Protection doesn’t fund mobilization. It gives you a buyer if a qualifying invoice goes unpaid. Before you start the job, ask Delos to review the subcontract and flag the first draw, any retainage, and any payment condition you’re relying on.